Below are details of all planned roadworks that affect our immediate area, some may be just outside the ward but could impact your daily travel. These are shown in date order.
Cleeve Green - 27.02.2026 - 26.03.2026 - Skip on road at rear of 63 Newton Road
Sheridan Road - 02.03.2026 - 29.03.2026 - Skip on road near 139 Sheridan Road
The Hollow - 16.03.2026 - 18.03.2026 - BANES - Feeder Pillar replacement, near junction with Kelston View, Footpath closed, some carriageway incursion
Haycombe Drive - 16.03.2026 - 18.03.2026 - Wessex Water - Domestic Leak near 184, Footpath closure
The Hollow - 16.03.2026 - 18.03.2026 - Openreach - to clear 3 blockages, outside 118 to 166, Footpath closed
Lower Bristol Road - 16.03.2026 - 18.03.2026 - ITS Technology Group - Utility and Maintenance repair, near Twerton Mill, some carriageway incursion
Shophouse Road - 16.03.2026 - 20.03.2026 - BANES - Installation of Zebra Crossing, full road closure
Kelston View - 17.03.2026 - 19.03.2026 - BANES - Feeder Pillar replacement, near junction with Wedgwood Road, some carriageway incursion
Watery Lane - 17.03.2026 - 20.03.2026 - Openreach - Laying new duct at Junction of Watery Lane and Newton Road, no carriageway incursion
Newton Road - 17.03.2026 - 20.03.2026 - Openreach - Laying new duct at Junction of Cleeve Green and Newton Road, Footpath closed and Bus Stop suspension in place
Haycombe Drive - 18.03.2026 - Openreach - Utility and Maintenance works, some carriageway incursion
The Hollow - 18.03.2026 - 20.03.2026 - Openreach - utility repair and maintenance works, some carriageway incursion
Little Hill - 20.03.2026 - 21.03.2026 - Mua Electricity Limited - new connection, Footpath closure
Lower Bristol Road - 20.03.2026 - 21.03.2026 - Mua Electricity Limited - Utility Asset Works opposite entrance to Weston Island, two way lights
Shophouse Road - 23.03.2026 - 02.04.2026 - BANES - Installation of traffic calming scheme, traffic lights in place
Freeview Road - 23.03.2026 - 27.03.2026 - BANES - Column replacement, some carriageway incursion
The Hollow - 08.04.2026 - 10.04.2026 - Wessex Water - Install water meter, outside 99 - 101 The Hollow, no carriageway incursion
The Hollow - 14.04.2026 - 21.04.2026 - National Grid - utility repair and maintenance work, multi way traffic lights
High Street - 20.04.2026 - 23.04.2026 - National Rail - Railway works, full road closure, this is by the railway arch leading into the High Street near McDonalds only, so a diversion will be in place at this location
Where roads are closed, we will provide full details of impacts on bus services (if applicable) closer to the date of the works.
Some work is added to this list at short notice and we will endeavour to let residents know as soon as we have been made aware.