Tuesday, 10 March 2026

Scheduled Roadworks in our area - March - May 2026

Below are details of all planned roadworks that affect our immediate area, some may be just outside the ward but could impact your daily travel. These are shown in date order.


Highland Road - 17.12.2025 - 10.03.2026 - Scaffolding outside 37 Highland Road, no carriageway incursion

The Hollow - 02.02.2026 - 13.03.2026 - National Grid - utility asset works, 4 ways traffic lights in place

Innox Road - 02.02.2026 - 13.03.2026 - National Grid - utility asset works, 4 ways traffic lights in place

Cleeve Green - 27.02.2026 - 26.03.2026 - Skip on road at rear of 63 Newton Road

Sheridan Road - 02.03.2026 - 29.03.2026 - Skip on road near 139 Sheridan Road

Haycombe Drive - 06.03.2026 - 10.03.2026 - Openreach - lay ducting and clear blockage near 225, Footpath closure

Cleeve Green - 06.03.2026 - 10.03.2026 - Openreach - lay ducting and clear blockage near number 75, footpath closure

Newton Road - 06.03.2026 - 10.03.2026 - Openreach - clear blockage, opposite 76, Footpath closure

Shophouse Road - 09.03.2026 - 11.03.2026 - Openreach - lay ducting, from junction with the High Street up to number 50 Shophouse Road, Footpath closure 

Cleeve Green - 10.03.2026 - 12.03.2026 - Openreach - clear blockage, opposite number 15, footpath closure

Kelston View - 13.03.2026 - 14.03.2026 - Openreach - Clear blockage in footpath cabling outside 100 - 102, traffic lights in place

The Hollow - 16.03.2026 - 17.03.2026 - Truespeed - utility asset works, Footpath closed, some carriageway incursion, outside number 18

Highland Road - 16.03.2026 - BANES - Full road closure, carriageway resurfacing

Pennyquick - 16.03.2026 - 18.03.2026 - Openreach - lay 10m of duct and construct a modular 4 box, near The Globe, traffic lights in place

The Hollow - 16.03.2026 - 18.03.2026 - BANES - Feeder Pillar replacement, near junction with Kelston View, Footpath closed, some carriageway incursion

The Hollow - 16.03.2026 - 18.03.2026 - Openreach - to clear 3 blockages, outside 118 to 166, Footpath closed

Shophouse Road - 16.03.2026 - 20.03.2026 - BANES - Installation of Zebra Crossing, full road closure

Kelston View - 17.03.2026 - 19.03.2026 - BANES - Feeder Pillar replacement, near junction with Wedgwood Road, some carriageway incursion

Watery Lane - 17.03.2026 - 20.03.2026 - Openreach - Laying new duct at Junction of Watery Lane and Newton Road, no carriageway incursion

Newton Road - 17.03.2026 - 20.03.2026 - Openreach - Laying new duct at Junction of Cleeve Green and Newton Road, Footpath closed and Bus Stop suspension in place

Shophouse Road - 23.03.2026 - 02.04.2026 - BANES - Installation of traffic calming scheme, traffic lights in place

Freeview Road - 23.03.2026 - 27.03.2026 - BANES - Column replacement, some carriageway incursion

The Hollow - 14.04.2026 - 21.04.2026 - National Grid - utility repair and maintenance work, multi way traffic lights

High Street - 20.04.2026 - 23.04.2026 - National Rail - Railway works, full road closure, this is by the railway arch leading into the High Street near McDonalds only, so a diversion will be in place at this location

Where roads are closed, we will provide full details of impacts on bus services (if applicable) closer to the date of the works. 

Some work is added to this list at short notice and we will endeavour to let residents know as soon as we have been made aware.